青田水利枢纽过鱼设施设计初探 |
Study on Design of Fish Passage in Qingtian Hydrojunction |
|
DOI: |
中文关键词:青田水利枢纽 诱导式垂直升降过鱼设施 鳗鲡 香鱼 |
英文关键词:Qingtian hydro-junction inductive verticle lifting fish pass facility Anguilla anguilla Plecoglossus altivelis |
基金项目: |
|
摘要点击次数: 2051 |
全文下载次数: 1691 |
中文摘要: |
青田水利枢纽是瓯江流域水利开发的最后一级水电站,过鱼对象为花鳗鲡(Anguilla marmorata)、鳗鲡(Anguilla anguilla)、香鱼(Plecoglossus altivelis)和中华绒螯蟹(Eriocheir sinensis)。过鱼对象的生态习性和游泳能力各不相同,且溯游能力均较弱,结合工程实际,设计修建由出水管道、“八字”形诱导网、集鱼网箱、起降机械和过鱼滑道5部分组成的“诱导式垂直升降过鱼设施”实现过鱼对象上行。 |
英文摘要: |
Qingtian hydro-junction was the last stage hydropower station for water development in Oujiang River.Auguilla marmorata,Auguilla auguilla,Plecoglossus altivelis and Eriocheir sinensis were taken as the fish pass objects with a low ability of swimming,and their ecological habit and swimming abilities were different from each other. Based on the engineering practice,the paper designed and constructed the inductive vertical lifting fish pass facility,which was composed by outlet pipe,bell shaped inductive net,net cage of attracting fish,landing machinery and fish pass slide. And this facility could make all the fish pass objects swim upstream. |
许强,朱俊杰,赵菲菲,杨永进,刘卫红.2013.青田水利枢纽过鱼设施设计初探[J].水生态学杂志,34(4):35-37. |